B1’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Updated R&T Plan 08/2020
2 R&T Plan 02/2019 DONE
3 List of potential R&T Partners and areas of interest 09/2018 DONE
4 Updated R&T Plan 08/2021
5 R&T Partner resources & capacities questionnaire responses 08/2019
6 Updated R&T Plan 08/2019
B1’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 R&T Workshop convened 12/2018 DONE
2 R&T Partners contacted 10/2018 DONE
3 Resources and capacities questionnaire issued 02/2019 DONE
B2’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Guidance document for chemical analysis of environmental contaminants in AP&P samples 08/2019
2 Guidance document for sampling, processing, archiving samples 08/2020
3 Guidance document on assessing quality of AP&P contaminants data 08/2021
B2’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Winter School convened 12/2018 DONE
2 Action B.1 review completed 08/2019
3 Draft guidance on chemical analysis of environmental contaminants in AP&P discussed at MEETING 3 04/2019
4 Draft guidance on sampling, processing, archiving samples discussed at MEETING 5 06/2020
5 Draft guidance on assessing quality of AP&P contaminants data discussed at MEETING 6 06/2021
B3’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 APEX Target Analyses Database (Module 2) and DCT 09/2019
2 APEX Non-target Screening (NTS) Analyses Database (Module 3) and DCT 10/2019
3 APEX Samples Database (Module 1) and DCT 12/2018
B3’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Data from Action B4 Tier 1 target and NTS analyses uploaded in Modules 2 and 3 09/2019
2 Data on samples from 25 European ESBs and NHMs uploaded in Module 1 11/2019
3 Data from Action B4 Tier 2 target and NTS analyses uploaded in the database 08/2020
4 Data on samples from total 50 ESBs and NHMs uploaded to Module 1 12/2020
5 Data from target and NTS analyses of Tier 2 and 3 (Action B4) uploaded in the database 07/2021
6 Data on samples from total 75 ESBs and NHMs uploaded to Module 1 02/2022
B4’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Data from targeted and NTS analyses of 100 Tier 1 samples available in APEX KnowledgeBase 08/2019
2 Data from targeted and NTS analyses of 54 Tier 2 samples available in APEX
KnowledgeBase
06/2020
3 Data from targeted and NTS analyses of up to 40 Tier 3 Samples available in APEX
KnowledgeBase
06/2021
4 Report on methodologies used and overview of data obtained by Tier 1 (wide-scope
screening), Tier 2 (time trend analysis) and Tier 3 (replication)
02/2022
B4’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Tier 2 Analyses completed 04/2020
2 Tier 3 Analyses completed 04/2021
3 Tier 1 Analyses completed 06/2019
B5’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 List of top prioritised 300 AP&P pollutants and associated PBT assessments 11/2021
2 A draft guideline for assessment of PBT properties of pollutants in AP&P samples 02/2022
3 A substance evaluation for 1 – 2 substances using monitoring data for the B-criterion 02/2022
B5’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Top 300 AP&P pollutants prioritised based on Tier 1 results 10/2019
2 Exposure assessment procedure for biocides in AP&P samples optimised and tested 08/2019
B6’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 A framework for monitoring terrestrial pollutants to assess the success of pan-European mitigation actions 02/2022
2 Two peer-reviewed papers on B6 approach, method and findings submitted for publication 02/2022
3 Guidelines for use of raptor species to monitor changes in terrestrial pollutants 08/2019
B6’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Results of country-scale analyses of ESBs and NHMs samples (144 samples) stored in DCTs and submitted for upload to AP&P Knowledgebase (module 1) 12/2020
2 Results of pan-European analyses of ESBs and NHMs samples (additional 144 samples) stored in DCTs and submitted for upload to AP&P KnowledgeBase (module 1) 08/2021
B7’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 List of predominant chemical mixtures in AP&P samples 02/2022
B7’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 A workflow for high-throughput statistical evaluation and visualisation tools established and tested 08/2021
C1’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Progress Monitoring Report on LIFE Performance Indicators (KPIs) 06/2021
2 Final Monitoring Report on LIFE Performance Indicators (KPIs) 11/2022
3 List of project performance indicators 11/2018 DONE
4 Project Baseline Report 11/2018 DONE
5 Mid-term Monitoring Report on LIFE Performance Indicators (KPIs) 02/2020
6 Ex post impact assessment 08/2022
7 Socio-economic impact assessment 08/2022
C1’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Mid-Term Monitoring Report on LIFE Performance Indicators (KPIs) 02/2020
2 Progress Monitoring Report on LIFE Performance Indicators (KPIs) 06/2021
3 Final Monitoring Report on LIFE Performance Indicators (KPIs) 11/2022
D1’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Notice board at each Beneficiary’s office 11/2018 DONE
2 Layman’s brochure/flyer 11/2018 DONE
3 2 policy briefs published 02/2022
4 Layman’s report 02/2022
5 Project website 11/2018 DONE
D1’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Press conference 1 convened 07/2020
2 Press conference 2 convened 04/2022
3 LIFE APEX corporate identify established 02/2019
4 LIFE APEX presented at 3 external conferences 08/2022
5 LIFE APEX presented at IESB and CETAF meetings 02/2019 DONE
D2’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 Protocols for regulatory application of novel approaches 04/2022
2 Report for chemicals producers and users 04/2022
D2’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 Review of use of chemical monitoring data in regulatory risk assessments 05/2019
2 Regulatory Advisory Board established 11/2018 DONE
E1’s PROJECT DELIVERABLE PRODUCTS
NAME DEADLINE STATUS
1 After-LIFE Plan 11/2022
2 Project policy on, and specific mechanisms for, green procurement 11/2018 DONE
E1’s PROJECT MILESTONES
NAME DEADLINE STATUS
1 PSC and sub-groups established 09/2018 DONE
2 PMG established 09/2018 DONE